Welcome to the City Communications update page on the approximate $70 million transformation of the former St. Mary’s Hospital campus into a new complex for the Police and Fire Departments, E911, Pension System offices and City Court operations. 

Visit here for regular updates, photos and videos on the project, as well as information on Lincoln Memorial University's $40 million investment in new nursing and dental schools at the site.

The City's new safety complex is scheduled to be substantially completed by late 2022, with staff move-ins to follow incrementally. Learn more at www.knoxvilletn.gov/safetycomplex.




Recent Posts
April 2020 - Posts
The original St. Mary's Hospital building, dating back to 1929, is being preserved. Crews this week will be completing masonry work to protect the exposed east-side exterior. Deputy to th ... more» 
Posted by evreeland  On Apr 28, 2020 at 11:37 AM
  
This week, Environmental Abatement Inc. crews are performing above-ceiling demolition on the 7th floor of the former Professional Office Building and mass demolition on the 6th floor, while also r ... more» 
Posted by evreeland  On Apr 14, 2020 at 6:14 PM
  
As contractor crews get into their second month of work at the site of a new $40 million Public Safety Complex in North Knoxville, demolition continues on the 6th floor of the former Professional ... more» 
Posted by evreeland  On Apr 13, 2020 at 3:24 PM
  
As demolition and site preparation on the former St. Mary's Hospital campus in North Knoxville move into April, the City's $46.5 million investment in a Public Safety Complex and adjoining space for p ... more» 