Stadium Update: Concrete Poured for Plazas, First Trees Planted, Streetscapes Improvements Under Way
The opening of Covenant Health Park is just a few months away - and work is underway both inside and outside the stadium.
Concrete is being poured for the four plazas surrounding the stadium. Together, they create a new public space that's larger than Market Square downtown.
The first street trees were planted last Friday in front of the stadium, in deep root boxes alongside Jackson Avenue.
And work has started on the Central Street and Willow Avenue Streetscape Project.
Here's a video showing what's new at the stadium:
According to Denark Construction, the stadium project will be completed comfortably ahead of schedule.
"The team at Denark is proud to be able to turn over the keys to the stadium to the Knoxville Smokies several months ahead of schedule to give them the opportunity to install their furniture, branding signage, and other elements that wrap up the stadium work in time for the April 15 Opening Day," Denark Vice President Will Rothermel said.
Meanwhile, as part of the streetscape project, new ADA flat and wide sidewalks are being built on the east side of Central Street between Willow and Summit Hill Drive, as well as along the south side of Willow Avenue.
New street lights are being installed, and 12 trees, including lacebark elms, will be planted.
Unsightly utility lines are being relocated below ground.
Due to construction - and, long term, the need for more room to accommodate pedestrians walking to and from the stadium - there is no longer any on-street parking on Willow Avenue.
Here's a gallery, showing some of the February work happening in and around the stadium:
Posted by
evreeland
On 11 February, 2025 at 12:31 PM
Tags
West Hills
South Knoxville
Cumberland Avenue
KAT
Website
communications
Cumberland
free fare
Christi Branscom
Knoxville Bar Foundation
roadwork
redevelopment
311
United Way
CAC
Market Square
CBID
Let's Move
Urban agriculture
community gardens
Beardsley Farm
kids
fountains
neighborhood
NUSA
Houston Texas
City People
IACMI
economic development
ORNL
Edgewood Park
music
community
James Agee
library
PrideFest
Henley Bridge
marriage
KPD
Rausch
public records
Festival on the 4th
Transit
Smart Growth
climate
sustainability
Parks
Bearden
Everly
Jackson Avenue
development
» more
Recent Posts
March 11, 2025 Knoxville Neighborhood Advisory Newsletter Available
March 4, 2025 Knoxville Neighborhood Advisory Newsletter Available
February 25, 2025 Knoxville Neighborhood Advisory Newsletter Available
February 18, 2025 Knoxville Neighborhood Advisory Newsletter Available
Wide, Tree-lined Sidewalks Will Connect to Stadium - and So Will Future Greenways
February 11, 2025 Knoxville Neighborhood Advisory Newsletter Available
Stadium Update: Concrete Poured for Plazas, First Trees Planted, Streetscapes Improvements Under Way
February 4, 2025 Knoxville Neighborhood Advisory Newsletter Available
January 28, 2025 Knoxville Neighborhood Advisory Newsletter Available
January 21, 2025 Knoxville Neighborhood Advisory Newsletter Available
Archives
March 2025 (2)
February 2025 (6)
January 2025 (9)
December 2024 (7)
November 2024 (4)
October 2024 (10)
September 2024 (4)
August 2024 (5)
July 2024 (6)
June 2024 (5)
May 2024 (4)
April 2024 (9)
Group Blogs
City Blog
KAT Blog
KPD News & Alerts
Magnolia Avenue Streetscapes Project
More...
Post Categories
City Events
City Services
Cumberland Ave.
Downtown
Government
KAT
Mayor Kincannon
Meetings
Neighborhoods
Outdoor & Recreation
Public Safety
Redevelopment
Road Work
Safety Complex
South Waterfront
Sustainability