August Updates on North Central Street Project 

PROGRESS SINCE JULY 26, 2018

  • All storm drainage in somplete except for Baxter Avenue

  • Signal and interconnect infrastructure in Bernard Avenue is complete

  • Signal poles installed at 5th, Broadway, and Bernard

  • Sidewalks, curbs, and bump outs are complete in Bearden Place intersection

  • Sidewalks at Regions Bank are complete

  • Mock up panels have been poured and reviewed
    a.  Light sandblast finish chosen pending on site confirmation

       b. Newport sand mix chosen over Nolichucky sand mix

  • Mulch installed from 5th Avenue to Bernard Avenue

PROGRESS SINCE AUGUST 9, 2018

  • All curbs, sidewalks, and patching in Broadway intersection is complete

  • Regions Bank driveway is complete

  • Central Filling Station driveway is complete

  • Signal and interconnect infrastructures at Baxter Avenue is ongoing

PROGRESS SINCE AUGUST 23, 2018

  • All curbs, sidewalks, and patching in Bernard Avenue intersection is complete

  • Planter curbs from Bernard to Dameron have been poured

  • Driveway for Broadway Restaurant Equipment has been poured

  • Bus shelter pads at Bernard and Dameron have been poured

  • Curbs on east side of Central from Bearden Place to the north entrance to All Occasion Catering have been poured

  • Signal and interconnect infrastructure at Baxter Avenue is complete


TWO-WEEK LOOK AHEAD

  • Signal system infrastructure work at Alexander Avenue

  • Curbs, gutter pans, and sidewalks from Pearl Place to Baxter Avenue

  • Resume storm work in Baxter after KUB gas line relocation is complete